Guaranteed Maximum Price in Construction in USA
Definition of Guaranteed Maximum Price (GMP) in U.S. Construction Contracts
In the U.S. construction industry, a Guaranteed Maximum Price (GMP) is a contractual agreement that establishes a ceiling on the total cost of a construction project. Under a GMP contract, the contractor agrees not to exceed a specified price for the entire project. If the actual costs are lower than the GMP, the savings may be shared between the contractor and the owner based on pre-agreed terms. If the costs exceed the GMP, the contractor absorbs the overrun, unless it results from approved changes or unforeseen conditions outside the original scope.
Key Components of a GMP Construction Contract
Maximum Price Limit
The foundation of a GMP contract is the fixed upper limit. This includes:
- Direct construction costs
- General conditions
- Contractor’s fee
- Contractor’s contingency
- Subcontractor fees
- Insurance and bonding
This maximum cap protects the owner from budget overruns, ensuring the project cost cannot exceed the agreed amount without formal modifications.
Open-Book Accounting
A GMP contract typically includes an open-book provision, which gives the owner full access to:
- Cost documentation
- Invoices
- Timecards
- Subcontractor contracts
- Material receipts
This transparency helps maintain financial accountability and builds trust throughout the construction process.
Contingencies and Allowances
A well-structured GMP includes defined contingency funds:
- Contractor’s contingency: Reserved for unexpected but non-scope-altering issues, such as coordination errors or field conditions.
- Owner’s contingency: Typically reserved for scope changes, upgrades, or enhancements initiated by the owner.
These funds are closely monitored and require justification and documentation for use.
Advantages of Using a Guaranteed Maximum Price Contract
Cost Control
The primary benefit of GMP contracts is the ability to control costs. The owner gains a clear financial ceiling, providing budget certainty throughout the duration of the project.
Incentive for Contractor Efficiency
Since the contractor bears the financial risk of overruns, GMP contracts motivate them to:
- Manage resources effectively
- Avoid delays
- Control subcontractor performance
- Minimize waste
Efficient management directly contributes to higher profit retention for the contractor when costs are kept under control.
Shared Savings Potential
A typical GMP contract allows for shared savings, encouraging collaboration between owner and contractor. If the total construction costs fall below the GMP:
- The owner saves money
- The contractor may receive a portion of the savings as a bonus
This model supports team-oriented project delivery and financial alignment.
Improved Collaboration and Transparency
The combination of early contractor involvement and open-book cost accounting promotes strong communication and trust between all stakeholders. Issues are often identified early and resolved proactively.
Common Sectors Using GMP Contracts in the USA
GMP agreements are frequently used in sectors that require strict budget management and public accountability, including:
- Healthcare construction (hospitals, clinics, research labs)
- Educational facilities (schools, universities, dormitories)
- Government projects (city halls, federal buildings, public libraries)
- Transportation infrastructure (airports, rail stations)
- Commercial developments (shopping centers, corporate offices, hospitality)
These sectors benefit from the balance of transparency and cost predictability offered by the GMP model.
How the GMP is Established in Construction Projects
Before a GMP contract is finalized, the following steps are taken:
Preconstruction Phase
The contractor is often engaged during design development, allowing them to:
- Analyze drawings
- Conduct constructability reviews
- Perform value engineering
- Prepare preliminary cost estimates
- Develop risk mitigation plans
This phase enables a more accurate GMP proposal based on a clear understanding of scope and project needs.
Cost Development and Scope Definition
The contractor assembles detailed cost estimates, using:
- Current market rates
- Subcontractor bids
- Labor rates and schedules
- Material lead times
The contractor, architect, and owner review the cost breakdown to ensure all elements are fully captured within the GMP package.
Formal GMP Proposal and Amendment
Once the estimate is finalized, the contractor presents a formal GMP Amendment. This includes:
- Itemized costs
- Allowances
- Schedule milestones
- Contingency funds
- Shared savings clauses
The amendment becomes part of the prime contract agreement.
Contract Terms and Provisions Specific to GMP Agreements
To support a successful GMP delivery, contracts typically include clauses related to:
- GMP adjustment procedures: Defines how changes in scope are incorporated
- Contingency tracking: Outlines how and when contingency funds can be used
- Reconciliation audits: Ensures proper allocation of costs and validates savings
- Final accounting: Conducted at project closeout to reconcile actual costs
These provisions help ensure that all financial elements are clearly documented and enforceable.
GMP vs. Other Construction Contract Types
GMP vs Lump Sum Contracts
A lump sum (fixed price) contract does not allow for open-book accounting. Once the price is set, any cost overruns or savings are solely the contractor’s responsibility. Unlike GMP:
- No cost transparency
- No shared savings
- Less flexibility for collaboration
GMP contracts offer more owner visibility and involvement.
GMP vs Cost-Plus Contracts
A cost-plus contract reimburses the contractor for actual costs plus a fee, with no cap unless a GMP clause is added. Pure cost-plus agreements:
- Offer maximum flexibility
- Provide little cost control
- Pose higher financial risk for the owner
The addition of a GMP converts cost-plus into a more owner-friendly delivery model.
GMP vs Time and Material (T&M) Contracts
T&M contracts are best for undefined scopes and small-scale work. The contractor is paid hourly plus material costs, with no cost ceiling. GMP contracts are preferred for larger, complex projects requiring financial certainty and transparency.
Risks and Challenges in GMP Construction Contracts
While GMP contracts favor owners in terms of cost protection, contractors face several risks:
- Estimating errors leading to cost overruns
- Design omissions or incomplete documents
- Market price escalations
- Unforeseen conditions
Contractors must manage these risks through thorough preconstruction planning, reliable cost data, and strategic procurement.
Project Delivery Methods That Use GMP Agreements
Construction Manager at Risk (CMAR)
In CMAR projects, the Construction Manager provides preconstruction services and commits to a GMP. This method supports:
- Collaborative planning
- Faster project delivery
- Defined risk management
The CM takes full responsibility for delivering the project within the GMP.
Design-Build with GMP
Design-Build combines design and construction under a single contract. When paired with a GMP, the owner benefits from:
- Integrated decision-making
- Schedule compression
- Controlled costs
Design-Build GMP is increasingly favored for fast-track public and private sector projects.
Best Practices for Managing GMP Construction Projects
To optimize performance in a GMP contract, project stakeholders should:
- Define scope clearly before GMP is set
- Maintain a transparent cost reporting system
- Monitor use of contingencies and allowances
- Conduct routine budget reconciliations
- Document change orders in real-time
- Implement a final cost audit and savings allocation
These practices ensure a cost-efficient project that delivers value to both owner and contractor.